# Submittal Package Incompleteness in Division 25 Integrated Automation submittals

> Source: https://deviationcheck.com/divisions/25-integrated-automation/submittal-package-incompleteness/

A required submittal element (cut sheet, schedule, calculation, sample) is missing, leaving the package unreviewable as submitted.

## What to look for in Division 25 Integrated Automation

Commonly required items in Div 25 specs:
- System architecture riser diagram showing all controllers, networks, and integration points
- Controller hardware cut sheets with point capacity and supported protocols
- Network architecture diagrams with IP/MSTP/LonWorks segment detail
- Sequences of operation (matched to mechanical spec sections)
- Points list with point names, types, and engineering units
- Graphics workstation hardware and software specifications
- Operator interface screenshots or mockups
- Integration protocol documentation for each connected subsystem
- Bill of materials with all controllers, sensors, actuators, and network devices
- Cybersecurity plan for building network segmentation
- Trending and data logging configuration details (points, intervals, retention period)
- Alarm priority matrix and notification routing plan
- Commissioning and functional performance test procedures
- Training plan and warranty documentation
- Spare parts list and recommended inventory

---

## Severity

Default grade: Fix and Resubmit. The sub completes the package and resubmits before the PM can fully review.