A required submittal element (cut sheet, schedule, calculation, sample) is missing, leaving the package unreviewable as submitted.

## What to look for in Division 21 Fire Suppression

Commonly required items in Div 21 specs:
- Sprinkler system shop drawings (piping layout, head locations, hanger locations)
- Hydraulic calculations (demand/supply analysis per NFPA 13)
- Sprinkler head cut sheets with UL/FM listing documentation
- Valve and trim product data
- Fire pump certified factory test curves
- Fire pump controller product data and wiring diagrams
- Seismic bracing calculations and layout
- Material certificates for pipe and fittings
- Alarm device product data (flow switches, tamper switches, pressure switches)
- Fire department connection (FDC) product data
- Backflow preventer product data and certification
- NICET designer certification documentation
- Contractor license documentation
- Sequence of operations for preaction/deluge systems
- Clean agent system design calculations and agent quantity

---

## Severity

Default grade: Fix and Resubmit. The sub completes the package and resubmits before the PM can fully review.