# Submittal Package Incompleteness in Division 11 Equipment submittals

> Source: https://deviationcheck.com/divisions/11-equipment/submittal-package-incompleteness/

A required submittal element (cut sheet, schedule, calculation, sample) is missing, leaving the package unreviewable as submitted.

## What to look for in Division 11 Equipment

Commonly required items in Div 11 specs:
- Equipment schedule with model numbers cross-referenced to drawings
- Utility rough-in drawings (gas, electric, plumbing, drain for each piece)
- Equipment cut sheets with full dimensional data (plan, elevation, utility connection locations)
- NSF/ANSI listing documentation for each foodservice item
- UL and AGA certification numbers
- Warranty documentation (compressor, parts, labor durations)
- Refrigerant type and charge weight
- Noise/sound data (dBA at specified distance) where specified
- Seismic anchorage details for equipment over 400 lbs (IBC Chapter 13)
- Energy compliance data (ASHRAE 90.1, ENERGY STAR verification)
- Maintenance and service access clearance diagrams
- Start-up and commissioning procedures for complex equipment (combi ovens, blast chillers, conveyor dishwashers)

---

## Severity

Default grade: Fix and Resubmit. The sub completes the package and resubmits before the PM can fully review.