# Submittal Package Incompleteness in Division 08 Openings submittals

> Source: https://deviationcheck.com/divisions/08-openings/submittal-package-incompleteness/

A required submittal element (cut sheet, schedule, calculation, sample) is missing, leaving the package unreviewable as submitted.

## What to look for in Division 08 Openings

Commonly required items in Div 08 specs:
- Hardware schedule cross-referenced to door schedule (every opening with hardware set)
- Keying schedule (master key system, construction keying, final keying)
- Curtain wall shop drawings with structural analysis
- Curtain wall thermal analysis (condensation resistance per AAMA 1503)
- Door/frame/hardware templates (shop drawings showing prep locations)
- Finish samples (hardware finishes, frame finishes)
- Glass mock-up details (for curtain wall projects)
- Fire-rated assembly documentation (complete UL/WHI listing with all components)
- Warranty documentation (hardware, glass, curtain wall system, finish)
- Wind load analysis for curtain wall and storefront
- Structural engineering for curtain wall anchorage
- ADA compliance verification for each accessible opening

---

## Severity

Default grade: Fix and Resubmit. The sub completes the package and resubmits before the PM can fully review.