# Submittal Package Incompleteness in Division 03 Concrete submittals

> Source: https://deviationcheck.com/divisions/03-concrete/submittal-package-incompleteness/

A required submittal element (cut sheet, schedule, calculation, sample) is missing, leaving the package unreviewable as submitted.

## What to look for in Division 03 Concrete

Commonly required items in Div 03 specs:
- Concrete mix design submittals with proportions and material sources
- Trial batch test results (strength, slump, air content)
- Reinforcing steel shop drawings (bar bending schedules, placing drawings)
- Mill test reports (MTR) for reinforcing steel
- Admixture product data and compatibility letters
- Formwork drawings and shoring/reshoring calculations
- Curing compound product data
- Precast concrete shop drawings with connection details
- Precast erection drawings and sequence
- Post-installed anchor calculations and ICC-ES ESR
- Cold weather / hot weather concreting plan
- Quality control plan (testing frequency, sampling procedures)
- Concrete placement plan for mass pours

---

## Severity

Default grade: Fix and Resubmit. The sub completes the package and resubmits before the PM can fully review.